Hydro One  Hydro OneHomeSearchSite MapContact UsIndustry Links
Hydro OneHydro One
About Hydro One Networks
Electrical Safety
Customers
Energy Efficiency Tips and Tools
Electricity Updates
Environment
In Your Community
Regulatory Affairs
Media Centre

Home > Electricity Updates

Electricity Updates

Hydro One connects new sources of electricity to Ontario's grid. Working together with generation customers, we connect their facilities to Ontario's electricity system and transport their electricity to the market. Hydro One is committed to providing timely connections for new generators.

Key factors to consider in the connection of generation facilities:

  • Distance between generator and the closest acceptable system connection
  • Effect on existing customers and safety of public and staff
  • Ability to deliver all electricity to consumers with no bottlenecks

Ontario Electricity Request for Proposals (RFPs)

200 MW Renewables III RFP
On July 12, 2005, the Ontario Ministry of Energy issued a Request for Proposals (RFP) in draft form for up to 200 megawatts (MW) of renewable energy supply from renewable generating facilities with a contract capacity of between 0.25 MW and 19.99 MW, inclusive. For details, go to the official RFP Web site at www.ontarioelectricityrfp.ca.

1000 MW Renewables II RFP
On June 17, 2005, the Ontario Ministry of Energy issued a Request for Proposals (RFP) for up to 1000 megawatts (MW) of renewable energy supply from renewable generating facilities with a contract capacity of between 20.0 MW and 200.0 MW, inclusive. For details, go to the official RFP Web site at www.ontarioelectricityrfp.ca.

2500 MW New Clean Generation and Demand Side RFP
On September 13, 2004, the Ontario Ministry of Energy issued a Request for Proposals (RFP) for 2,500 megawatts (MW) of new clean generation (including co-generation and distributed generation), demand response, and demand-side management.

300 MW Renewables' RFP
On June 24, 2004, the Ontario Ministry of Energy issued a Request for Proposals (RFP) to solicit approximately 300 megawatts (MW) of capacity from new renewable generating facilities.

Working with you for the RFP

In the Pre-Bid process proponents need to work with Hydro One for a Preliminary Connection Assessment. Hydro One has developed a fast-track process that provides preliminary assessments to proponents wishing to submit a bid. In trying to meet the increased demand for assessments in the limited time period, it is imperative that ALL required data be submitted and that only one connection option be included per project or bid.


Pre- Bid: For proponents who are not engaged in the connection process, preliminary assessment/agreement are available. Generator covers this cost. Successful proponents will receive these details once selected
Approvals and Regulations External to Hydro One

Connecting your generation project to our transmission or distribution system requires approvals and following rules and codes from various bodies and regulators that govern the electricity business in Ontario.



Would you like to know more about Hydro One's generation connection process?

Still have questions?
If you are interested in connecting a generation facility to Hydro One's system, please e-mail gen.connect@hydroone.com or call 1-866-280-7712.

If you are planning to install a generator that employs a renewable technology and is less than 50 kW, please consider our Net Metering program. All residential and solar panel installations would benefit from this program, as would small wind turbines. Please visit our Net Metering site or call 1-877-447-4412 for information.

 

 

 

[ Printable Version ]

All contents © 2004 Hydro One Networks Inc. All rights reserved.
Privacy and Terms of Use