|
Home > Customers > Generators
For proposed projects connecting to Hydro One's
transmission system, Hydro One will work with you to complete the following
items. Note: The templates can be accessed online. Proponents
are recommended to carefully review the RFP submission requirements related
to the IESO and Hydro One reviews. Contact Hydro One's Generation Connections
Department at 1-866-280-7712 if you have questions about your Hydro
One transmission connection application.
For the 1000 MW Combined Heat and Power RFP:
1) Complete and sign the Transmission
Preliminary Study Agreement (Combined Heat and Power RFP) for the
project's Preliminary Customer Impact Assessment. This requires a payment
to Hydro One and includes a description of the scope of work.
2) Complete the Transmission
System Connection Application Form required for the project's Preliminary
Customer Impact Assessment.
For the 200 MW Renewables III RFP:
1a) Complete and sign the Transmission
Preliminary Study Agreement for new projects where the Generator
has not executed a Preliminary Customer Impact Assessment Agreement
with Networks or projects that have already been assessed as
part of the 300 MW or 1000 MW Renewables' RFP but there is an increase
or decrease in MW size that is 10% or more; OR for projects that
are either identical in MW size or the increase or decrease in MW size
is less than 10% and identical in technology, location, connection point
and connection arrangements to projects already assessed as part of
the 300 MW or 1000 MW Renewables' RFP.
1b) For all other projects that do not fit in the above categories
please e-mail gen.connect@hydroone.com or call 1-866-280-7712.
2) Complete the Transmission
System Connection Application Form required for the project's Preliminary
Customer Impact Assessment.
For the 1000 MW Renewables II RFP:
1) Complete and sign the Transmission
Preliminary Study Agreement for new applicants or for
applicants who have bid on the previous 300 MW renewable RFP for
the project's Preliminary Customer Impact Assessment. This requires
a payment to Hydro One and includes a description of the scope of work.
2) Complete the Transmission
System Connection Application Form required for the project's Preliminary
Customer Impact Assessment.
Note: Please confirm the requirements for the RFP in the Government RFP's official releases. Questions on RFP issues should be directed to the Government's official RFP Web site at www.ontarioelectricityrfp.ca.
To help bidders meet the tight deadlines of the Government RFP, we
have an expedited process for providing a Preliminary
Customer Impact Assessment.
Generators must apply to the Independent Electricity System Operator (IESO) for a System Impact Assessment.
back to top
Helping you meet RFP Deadlines
To meet the RFP's accelerated timelines, Hydro One has modified its normal
processes. For both the transmission and distribution connection processes,
the normal time required for assessment and estimating exceeds the RFP
timelines. Hydro One has developed expedited processes to provide preliminary
assessments and preliminary cost estimates to proponents. In trying to
meet the increased demand for assessments and work within the limited
time, it is imperative that ALL required data be submitted with the application.
back to top
Approvals and Regulations External to Hydro One
Connecting your generation project to our transmission or distribution
system requires approvals from and following the rules and codes of various
bodies and regulators that govern the electricity business in Ontario.
Here are the organizations you will need to work with on your way to connection.
Independent Electricity System Operator (IESO) - System
Impact Assessment
The Independent Electricity System Operator (IESO) manages Ontario's
power grid, provides the hourly energy spot market prices, and provides
the Market Rules for participating in the Ontario electricity market.
Participation in the Renewable Energy Supply Contract requires applying
to the IESO to become a registered market participant and complying
with all market rules including metering requirements.
A System Impact Assessment is conducted by the IESO for generating
facilities 10MVA or greater connecting to the distribution system, and
for all generating facilities connecting to the transmission system.
Ontario Energy Board (OEB)
The Ontario Energy
Board regulates Ontario's electricity and gas industry.
The OEB's
Distribution System Code (DSC) sets out the minimum conditions that
an Ontario distributor must meet in carrying out its obligations to
distribute electricity in Ontario under its license. Included in the
DSC are conditions applying to all transactions and interactions between
distributors and generators.
The Transmission
System Code (TSC) sets out the minimum conditions that an Ontario
transmitter must meet in carrying out its obligations to transmit electricity
in Ontario under its license. The TSC includes conditions applying to
all transactions and interactions between a transmitter and generators.
The Ontario
Energy Board Act, 1988, Section 57, requires that electricity market
participants be licensed in order to generate, deliver or sell electricity
in the province. Application
forms for licenses are available for generators, transmitters, distributors,
wholesalers, and retailers.
Board approval is required for the construction of electricity
transmission lines two kilometres or longer in length - see Filing
Requirements for Electricity Transmission Facilities Applications.
Ontario Ministry of Environment (MOE)
The Ontario
Ministry of Environment sets environmental standards for electricity
projects in Ontario and ensures that generators, distributors and transmitters
follow strict rules
and standards when constructing and operating facilities.
Environment
Assessment Regulation for Electricity Projects O.Reg. 116/0, provides
the environmental assessment regulations for generation, transmission
and high voltage distribution facilities.
Guide
to Environmental Assessment for Electricity Projects provides the
environmental assessment requirements for electricity projects. They
apply equally to the public and private sectors.
Electrical Safety Authority (ESA)
Ontario's Electrical
Safety Authority sets and enforces standards for electrical safety
through the Ontario Electrical Safety Code. Before connecting to Hydro
One's system, generating facilities are required to have the ESA inspect
their facility and provide Connection Authorization.
Canadian Environmental Assessment Agency
The Canadian Environmental
Assessment Agency controls the federal
environmental assessment process and it applies whenever a federal
authority has a specified decision-making responsibility for a project.
back to top
Would you like to know more about Hydro One's generation
connection process?
Still have questions?
If you are interested in connecting a generation facility to Hydro One's
system, please e-mail gen.connect@hydroone.com
or call 1-866-280-7712.
If you are planning to install a generator that employs a renewable technology
and is less than 500 kW, please consider our Net Metering program. All
residential and solar panel installations would benefit from this program,
as would small wind turbines. Please visit our Net
Metering section or call 1-877-447-4412 for information.
back to top
|