|
Home > Customers > Generators
For proposed projects connecting to Hydro One's
distribution system, Generators participating in the RFP need to work
with Hydro One to fulfill the following components for their bid. The
templates can be accessed online.
For the 1000 MW Combined Heat and Power RFP:
1) Complete and sign the Preliminary
Study Agreement for Generating Facilities 10 MVA or Greater, or
for Generating
Facilities for Less than 10 MVA. This requires a payment to Hydro
One and includes a description of the scope of work.
2) Complete the Distribution
System Connection Application Form and provide supporting documents.
This is required for the Preliminary Connection Impact Assessment.
For the 200 MW Renewables III RFP:
1) Complete and sign the Preliminary
Study Agreement for Generating Facilities 10 MVA or Greater, or
for
Generating Facilities for Less than 10 MVA. This requires a payment
to Hydro One and includes a description of the scope of work.
2) Complete the Distribution
System Connection Application Form and provide supporting documents.
This is required for the Preliminary Connection Impact Assessment.
Note: Please confirm the requirements for the RFP in the Government
RFP's official releases. Questions on RFP issues should be directed to
the Government's official RFP Web site at www.ontarioelectricityrfp.ca.
To help bidders meet the tight deadlines of the Government RFP, bidders
can use an expedited process, which provides a Preliminary
Distribution Connection Impact Assessment.
If the planned generation capacity is 10 Mega Volt Amperes (MVA) or greater,
the generator is also required to complete and submit an application for
a System Impact Assessment to the IESO.
The technical requirements generators must meet to connect to Hydro One's
distribution system are outlined in Technical
Requirements for Generators Connecting to Hydro One's Distribution System.
These requirements are in place to ensure public and employee safety,
protect the integrity of Hydro One's system and provide reliable and quality
service to our customers. The generator is responsible for the protection
of its own facilities and personnel.
For the RFP process, the proponents submit their application for a Distribution
Connection Impact Assessment. The "application" will consist of
a Preliminary Study Agreement, the application form and required supporting
documents.
back to top
Helping you meet RFP Deadlines
To meet the RFP's accelerated timelines, Hydro One has modified its normal
processes. For both the transmission and distribution connection processes,
the normal time required for assessment and estimating exceeds the RFP
timelines. Hydro One has developed expedited processes to provide preliminary
assessments and preliminary cost estimates to proponents. In trying to
meet the increased demand for assessments and work within the limited
time, it is imperative that ALL required data be submitted with the application.
back to top
Approvals and Regulations External to Hydro One
Connecting your generation project to our transmission or distribution
system requires approvals from and following the rules and codes of various
bodies and regulators that govern the electricity business in Ontario.
Here are the organizations you will need to work with on your way to connection.
Independent Electricity System Operator (IESO) - System
Impact Assessment
The Independent Electricity System Operator (IESO) manages Ontario's
power grid, provides the hourly energy spot market prices, and provides
the Market Rules for participating in the Ontario electricity market.
Participation in the Renewable Energy Supply Contract requires applying
to the IESO to become a registered market participant and complying
with all market rules including metering requirements.
A System Impact Assessment is conducted by the IESO for generating
facilities 10MVA or greater connecting to the distribution system, and
for all generating facilities connecting to the transmission system.
Ontario Energy Board (OEB)
The Ontario Energy
Board regulates Ontario's electricity and gas industry.
The OEB's
Distribution System Code (DSC) sets out the minimum conditions that
an Ontario distributor must meet in carrying out its obligations to
distribute electricity in Ontario under its license. Included in the
DSC are conditions applying to all transactions and interactions between
distributors and generators.
The Transmission
System Code (TSC) sets out the minimum conditions that an Ontario
transmitter must meet in carrying out its obligations to transmit electricity
in Ontario under its license. The TSC includes conditions applying to
all transactions and interactions between a transmitter and generators.
The Ontario
Energy Board Act, 1988, Section 57, requires that electricity
market participants be licensed in order to generate, deliver or sell
electricity in the province. Application
forms for licenses are available for generators, transmitters, distributors,
wholesalers, and retailers.
Board approval is required for the construction of electricity
transmission lines two kilometres or longer in length - see Filing
Requirements for Electricity Transmission Facilities Applications.
Ontario Ministry of Environment (MOE)
The Ontario
Ministry of Environment sets environmental standards for electricity
projects in Ontario and ensures that generators, distributors and transmitters
follow strict rules
and standards when constructing and operating facilities.
Environment
Assessment Regulation for Electricity Projects O.Reg. 116/0, provides
the environmental assessment regulations for generation, transmission
and high voltage distribution facilities.
Guide
to Environmental Assessment for Electricity Projects provides the
environmental assessment requirements for electricity projects. They
apply equally to the public and private sectors.
Electrical Safety Authority (ESA)
Ontario's Electrical
Safety Authority sets and enforces standards for electrical safety
through the Ontario Electrical Safety Code. Before connecting to Hydro
One's system, generating facilities are required to have the ESA inspect
their facility and provide Connection Authorization.
Canadian Environmental Assessment Agency
The Canadian Environmental
Assessment Agency controls the federal
environmental assessment process and it applies whenever a federal
authority has a specified decision-making responsibility for a project.
back to top
Would you like to know more about Hydro One's generation
connection process?
Still have questions?
If you are interested in connecting a generation facility to Hydro One's
system, please e-mail gen.connect@hydroone.com
or call 1-866-280-7712.
If you are planning to install a generator that employs a renewable technology
and is less than 500 kW, please consider our Net Metering program. All
residential and solar panel installations would benefit from this program,
as would small wind turbines. Please visit our Net
Metering section or call 1-866-280-7712 for more information.
back to top
|