![]() | ![]() ![]() |
|
|
Home > In Your Community > New Projects > Transmission System Projects
New Projects Transmission System Projects Western Brampton Transmission Reinforcement What's New October 9, 2007 On October 9, 2007, the Ontario Energy Board (OEB) issued a Decision
and Order granting Hydro One Networks Inc. leave to construct electricity
transmission facilities in the City of Brampton. April 26, 2007
The Project The proposed underground lines would be constructed completely within
an existing transmission corridor, which extends from Hydro One Brampton's
Jim Yarrow Municipal Transformer Station (MTS) at Steeles Ave and Chinguacousy
Rd. to Hydro One's planned Hurontario Station located on the Parkway Belt
near Hurontario St. and Hwy 407. The two new underground cable circuits
will extend about 3 kilometres in length (see map below). There is currently
an existing 230 kV overhead transmission line located on this corridor,
which will not be modified.
Environmental Approval Process The project is subject to provincial Environmental Assessment (EA) Act approval in accordance with the Class EA for Minor Transmission Facilities. The Class EA process falls is an effective way of ensuring that minor transmission projects that have a predictable range of effects are planned and carried out in a manner which is environmentally acceptable.
Following a consultation process with members of the public, government
agencies and municipalities, a draft Environmental Study Report (ESR)
is made available for stakeholder review and comment for a 30-day period.
If no concerns are expressed during the 30-day review period, the project
is considered to be acceptable. The final ESR is then filed with the Ministry
of the Environment and approval is granted. If concerns are expressed during the 30-day review period, Hydro One
will attempt to resolve them to complete the EA process. If Hydro One
cannot satisfy all of the concerns, a stakeholder may submit a "bump-up"
request for an individual Environmental Assessment of the proposed undertaking.
Hydro One will then consider whether a re-designation of the project is
appropriate, and send its response, the draft ESR and the individual's
bump-up request to the Minister of the Environment for a decision as to
whether or not the project requires an Individual EA or if the project
should be approved as proposed. Ontario Energy Board Approval The project also requires approvals under the Ontario Energy Board
(OEB) Act. Pending these approvals, the expected in-service date for
the project would be mid-2009. Public Information Centres
Public Information Centre #1
For more information, please contact:
EA Coordinator, Hydro One Tel: 416-345-6843 Fax: 416-345-6919 Email: Kimberly.Miller@hydroone.com |
All contents © 2007 Hydro One Networks Inc. All rights
reserved.
Privacy and Terms
of Use