Hydro One  Hydro OneHomeSearchSite MapContact UsIndustry Links
Hydro OneHydro One
About Hydro One Networks
Electrical Safety
Customers
Energy Efficiency Tips and Tools
Electricity Updates
Environment
In Your Community
Regulatory Affairs
Media Centre
Careers

Home > In Your Community > New Projects > Transmission System Projects

Electricity Updates

Transmission System Projects

Nobel Station

What's New - April 2008

Download the final Class EA Environmental Study Report (PDF 3.7 MB) for the Nobel Station project.

Project Background & Need

The existing high-voltage transmission system between Sudbury and Barrie is currently, just adequate to meet today's power transfer needs. The system has no capacity to accommodate increased generation.

The development of major renewable energy generation in northern Ontario has created a need to increase the capacity of this high-voltage transmission system to deliver more electricity between northern and southern Ontario. This need was identified by the Independent Electricity System Operator in its June 2006 Ontario Reliability Outlook and confirmed by the Ontario Power Authority.

To address this need, Hydro One proposes to build a new transmission station at the midpoint of the two existing 500-kV transmission lines between Hanmer Transformer Station (TS) in Sudbury and Essa TS outside of Barrie. The proposed Nobel Station will increase the flow of electricity between northern Ontario and southern Ontario by about 600 megawatts. The proposed in-service date is September 2009. Together with the extension of the generation rejection scheme in the northeast, the capability of the existing lines will be increased by up to 1000 MW.

Alternative Sites

In 1988, Ontario Hydro (predecessor of Hydro One) undertook a site selection and environmental assessment for a proposed switching station to increase power transfer capability of the two 500-kV transmission lines along the the 500 kV transmission corridor connecting Hamner TS in Sudbury and Essa TS outside of Barrie. Following a consultation process with municipal officials, provincial agencies, directly affected landowners and the general public, a preferred location was selected based on a comparison of the technical, environmental and landuse characteristics of seven locations. Although the project was approved and the property purchased by Ontario Hydro, the proposed Nobel Switching Station was not constructed since the forecast load growth did not materialize and generation development in the North was uncertain at that time. For more information, read the 1988 Nobel Switching Station Class EA Report (PDF 4.1 MB).

Preferred Site

The proposed Nobel Station would be located on Hydro One property in the Municipality of McDougall, approximately 700 metres south of the community of Waubamik and about 6 km southwest of the community of Nobel. The location of the station was chosen near Parry Sound (approximately 20 km to the south) as this is the midpoint between Sudbury and Barrie and the optimal location for improving the transmission flow from north to south. The station would be approximately 4 hectares in size.

Proposed Nobel Station Site Relocation

Subsequent to the Public Information Centre held on December 7, 2006 and initiation of the 60-day draft ESR review period, Hydro One staff has had an opportunity to revisit the proposed Nobel Station site area. Based on public input and additional technical information, Hydro One proposes to relocate the proposed Nobel Station from directly adjacent to transmission tower 401 further north (approximately 250 metres) to a location of lower gradient between transmission towers 401 and 400. In addition, the station equipment will be situated on two adjacent footprints as shown on the map below. This relocation further increases the distance between the proposed Nobel Station and the nearest residence, eliminates its visibility from the Hydro One right-of-way on the top of grade on the south side of Kirkham Road (and from adjacent residential property on Kirkham Road) and takes advantage of flatter terrain, eliminating the need to blast bedrock outcrops and minimizing the use of fill material and grading.

Nobel Station Proposed Relocation

Access Road Analysis and Selection of Preferred Route

As indicated in the draft ESR, initially three potential access routes were being considered. All are existing roads/trails which are accessible from Kirkham Road:

  • Pete's Hill Road to the east;
  • Fire Route 208 to the west; and
  • Off Kirkham Road at the Hydro One corridor along the Ontario Federation of Snowmobile Clubs Trail C.

Direct access from Kirkham Road (at the point where the Hydro One eastern transmission line intersects the road) was rejected as an option due to the need for blasting and associated effects on nearby residents; potential interference with a major snowmobile trail; and the potential for increased entry to the Hydro One property by unauthorized traffic directly from Kirkham Road.

The Pete's Hill Road access was rejected as an option due to the potential conflict with CN railway operations (immediately adjacent to the south of the route), the presence of a steep grade, the need for significant upgrading of the road and the greater route length.

Access using Fire Route 208 is the preferred option since the road is in good condition and requires the least upgrading. Further access to the north to the Nobel Station site would be provided by the Hydro One western transmission line corridor which will also facilitate tapping operations between the proposed Nobel Station and the western transmission line. The proposed access road from the western transmission line corridor through the forested area to the station will also provide for greater security from unauthorized entry since it is more remote and a greater distance from Kirkham Road. Entry to the site will be further restricted at the right-of-way/forested area interface.

Click to download PDF version
(click to enlarge)

Proposed Transmission Facilities

The proposed Nobel Station (see picture of similar station) will enable Hydro One to maximize the use of the existing transmission lines. It will also help to supply the Province of Ontario with clean and affordable renewable energy.

Major station equipment will include:

Stakeholder Consultation

Hydro One is seeking public feedback on the proposed location of Nobel Station. Our Public Information Centre (PIC) will provide you with an opportunity to review display panels and maps describing the proposed Nobel Station and the Class EA process; to comment on the proposed project; and to learn about the next steps in the approval process.

Public Information Centre
Tuesday, December 12, 2006
4:00 – 8:00 p.m.
Waubamik Community Hall
Highway 124, Waubamik, Ontario

Download the PIC Newspaper Advertisement (PDF 79 KB)
Download the PIC Informational Panels (PDF 483 KB)

Environmental Approval Process

Hydro One has initiated an Environmental Assessment (EA) in accordance with the Class Environmental Assessment for Minor Transmission Facilities. The Class EA process falls under the Ontario Environmental Assessment Act and is an effective way of ensuring that minor transmission projects that have a predictable range of effects are planned and carried out in a manner which is environmentally acceptable.

Following a consultation process with members of the public, government agencies and municipalities, a draft Environmental Study Report (ESR) is made available for stakeholder review and comment for a 30-day period. If no concerns are expressed during the 30-day review period, the project is considered to be acceptable. The final ESR is filed with the Ministry of the Environment and approval is granted.

If concerns are expressed during the 30-day review period, Hydro One will attempt to resolve them to complete the EA process. If Hydro One cannot satisfy all of the concerns, a stakeholder may submit a "bump-up" request for an individual Environmental Assessment of the proposed undertaking. Hydro One will then consider whether a re-designation of the project is appropriate, and send its response, the draft ESR and the individual's bump-up request to the Minister of the Environment for a decision as to whether or not the project requires an Individual EA or if the project should be approved as proposed.

Next Steps

The planning and analysis for the proposed project site is documented in Hydro One's Draft Environmental Study Report (ESR). The ESR is available for a 60-day public review period starting on January 5, 2007. Copies are available for download below, or can be obtained from your local public library or municipal office.

Download the Newspaper Ad - Notice of Completion of Class EA (PDF 80 KB)
Download the Draft Environmental Study Report (PDF 4.8 MB)

Timeline - Nobel Station


For more information, please contact:

    Heather Zhang
    Hydro One Networks Inc.
    483 Bay Street, 13th Floor, North Tower
    Toronto, ON M5G 2P5

    Tel: 1-877-345-6799 or 416-345-6799
    Fax: 416-345-6919
    E-mail: heather.zhang@HydroOne.com

 

 

[ Printable Version ]

All contents © 2008 Hydro One Networks Inc. All rights reserved.
Privacy and Terms of Use