|
 |
Home > In Your Community > New Projects > Transmission System Projects
Last Updated January 4, 2005
Transmission System Projects
Niagara Reinforcement - Transmission Line Project
Background
The Niagara Reinforcement project involves upgrading existing transmission
lines in the Niagara Peninsula between Niagara Falls and Middleport, south
of Hamilton. See
detailed map (PDF 2.3 MB). This work received Environmental Assessment
Act Approval in 1998 as part of the Niagara River Hydroelectric Development.
The reinforcement project includes:
- Replacing an existing double circuit 115 kV transmission line with
a double circuit 230 kV transmission line between Allanburg TS located
in Thorold and Caledonia TS located in Caledonia (65 km)
- Constructing a new double circuit 230 kV transmission line between
Caledonia TS and Middleport TS located near Caledonia (11 km)
- Some existing transmission lines and towers between Allanburg TS and
Sir Adam Beck Generating Station, and between Middleport TS and Burlington
TS may require minor upgrades.

See
detailed map (PDF 2.3 MB)
The need for these facilities was identified in the 10-year Outlook Report
by the Independent Electricity System Operator (for 2004-2013) and was
assessed in more detail by Hydro One. Project construction is expected
to begin during the summer of 2005 with the new facilities scheduled to
be in service by summer 2007.
The project will increase electrical power transfer capability between
the Niagara Falls area and the rest of the province by approximately 800
MW. In addition, it will provide the following benefits:
- Facilitate new generation development in the Niagara Falls area
- Reduce the risk of supply shortages
- Allow for more efficient use of existing generation resources
- Reduce transmission line losses.
All proposed system upgrades will occur within existing Hydro One transmission
corridors and station properties, with the exception of a small parcel
of land (less than 0.5 km) that would have to be acquired from the Ministry
of Transportation.
The Niagara Reinforcement project is subject to Ontario
Energy Board Approval under Section 92 of the Ontario Energy Board
Act, 1998.
Timeline
Click on a timeline box below for more details.

If you have a question, or would like to be notified when we've added
new information to our site, please contact:
Community Relations
Hydro One Networks Inc.
Tel: 1-877-345-6799 or 416-345-6799
Fax: 416-345-6984
E-mail: community.relations@HydroOne.com
| Niagara Reinforcement
- Transmission Line Project - Details |
|

1998
Approval of Niagara
River Hydroelectric Environmental
Assessment
|
|
In 1991, the former Ontario Hydro conducted and submitted an Individual
Environmental Assessment (EA) on the proposed Niagara River Hydroelectric
Development to the Ministry of Environment (MOE) in accordance with
the Environmental Assessment Act, 1976. The EA addressed both the
proposed expansion of the Sir Adam Beck generating station and the
transmission line upgrades. In 1998, the MOE granted the approval
of the Niagara River Hydroelectric Development EA which included
the preferred transmission line upgrade route.
Transmission line upgrades on the approved route have not been
constructed to date. Hydro One, a successor company of Ontario Hydro,
is now proposing the construction of the transmission line upgrades.
While it is not a requirement under the Act to seek additional EA
approvals, Hydro One committed to submit an update to the approved
EA to the MOE. Hydro One has finalized the update to the EA and
will submit it to the MOE before year-end.
Download the Order in Council and Notice
of Environmental Approval (PDF 1.6 MB).
|
|
|
|

May/June 2004
Meet with local utilities, municipal and regional officials to discuss
project
|
|
A series of meetings regarding
the Niagara Reinforcement Project were conducted with senior staff
of the Niagara Region and its municipalities (City of Thorold, City
of Niagara Falls, Town of Pelham and Township of West Lincoln). Meetings
were also held with the City of Hamilton, Brant County, Haldimand
County, a major transmission-connected customer, and local utilities
(Brant County Power, Haldimand County Power and Peninsula West Utilities).
At these meetings, Hydro One presented information about the Niagara
Reinforcement Project and discussed potential issues related to the
project with municipal staff.
Download the presentation
from these meetings (PDF 771 KB).
|
|
|
|

July/August 2004
Public consultation process
|
|
Hydro One held seven Public
Information Centres, including one at the Six Nations of the Grand
River, in order to provide stakeholders and the public with an opportunity
to review the Niagara Reinforcement Project plans and to provide input
to the planning process. The locations and dates of the information
centres were as follows:
- July 20, 2004 - Caledonia - Lion's Hall
- July 22, 2004 - Smithville - Twp. of West Lincoln Municipal
Building
- July 28, 2004 - Thorold - Allanburg Community Centre
- August 10, 2004 - Ohsweken - Six Nations Community Centre
- August 11, 2004 - Caledonia - Lion's Hall
- August 17, 2004 - Smithville - Twp. of West Lincoln Municipal
Building
- August 18, 2004 - Thorold - Allanburg Community Centre
The following public notices were published in newspapers to advertise
the information centres:
Download the information
panels from the Public Information Centres (PDF 4.9 MB).
|
|
|
|

October 2004
Section 92 evidence submitted to the Ontario Energy Board
|
|
On October 29, 2004 Hydro One applied to the Ontario Energy Board
for an order granting leave to construct transmission facilities
in the Niagara area. The application was supported by written evidence
that details the proposal for the new transmission lines. Hydro
One has requested a written hearing.
View the submissions
to the OEB.
|
|
|
|

December 2004
Environmental Update
filed with the Ministry of Environment
(Phase I & Phase II)
|
|
Hydro One committed to submit an update to the previously approved
Environmental Assessment of 1998. This update was accomplished in
two phases:
- During Phase I (2003), Hydro One confirmed the validity of the
preferred route selection and identified components of the environment
that might have been expected to change in the years since the
EA was prepared.
- During Phase II (2004), Hydro One gathered data on the components
of the environment that were identified as requiring further investigation
in Phase I.
Hydro One also undertook public and agency consultations and held
discussions with potentially affected First Nations. Additionally,
the update addresses mitigations for potential environmental effects.
Hydro One has finalized the update to the EA and will submit it
to the Ministry of Environment before year-end.
View the Phase
1 Update (PDF 3.3 MB).
View the Phase
2 Update (PDF 26.3 MB - High-speed Internet connection required).
|
|
|
|

Winter/Spring 2004
OEB approval process
|
|
As of December 17th, 2004, the timeline for review of the Niagara
Reinforcement Project submission is as follows:
October 29, 2004 - Application & evidence filed with
the OEB
November 17, 2004 - Letter of Direction on Notice
December 1, 2004 - Notice of Application published
December 15, 2004 - Deadline for intervenors to register
December 23, 2004 - Deadline for objections to written hearing
January 10, 2005 - Deadline for interrogatory questions to
Hydro One Networks
January 24, 2005 - Responses by Hydro One Networks to interrogatories
January 31, 2005 - Supplementary interrogatory questions
to Hydro One Networks
February 10, 2005 - Responses by Hydro One Networks to supplementary
interrogatories.
|
|
|
|
|
|