Hydro One  Hydro OneHomeSearchSite MapContact UsIndustry Links
Hydro OneHydro One
About Hydro One Networks
Electrical Safety
Customers
Energy Efficiency Tips and Tools
Electricity Updates
Environment
In Your Community
Regulatory Affairs
Media Centre

Home > In Your Community > New Projects > Transmission System Projects

Electricity Updates

Last Updated January 23, 2008

Transmission System Projects - Supply to Downtown Toronto

What's New

  • The tunnel linking Hydro One's Esplanade Transformer Station and John Transformer Station in downtown Toronto is now complete.
  • Final commissioning work is well underway to allow the new double circuit 115 kV underground transmission line in the tunnel to go into service in January 2008.
  • Hydro One is consulting with residents who live in the vicinity of Esplanade Transformer Station on site improvement options, including a new perimeter fence/wall and landscaping to be installed in 2008.
  • See photos of construction progress below.

Background

Toronto is Canada's largest city and plays a significant role in both the provincial and national economy. Hydro One transmits power to Toronto Hydro, the local distribution company that distributes electricity to customers in the city. A safe and reliable supply of electricity to the city is critical to the continued growth and prosperity of both Toronto and Ontario. This is especially true for the downtown core, home to the Toronto Stock Exchange, many corporate head offices and a significant number of diverse industries and commercial activity.

Link to route alternativesThe need for electricity in Toronto is forecast to continue to grow at a steady pace. This growing demand for electrical supply means upgrading the transmission system serving downtown to maintain reliable electricity supply to the city. Hydro One and Toronto Hydro, the local distribution company, agree that new facilities are required. Within Hydro One's 10 year planning period a new supply path to central Toronto will be required. However, a more immediate need is to reinforce the existing transmission infrastructure. This will improve the reliability of supply to downtown Toronto.

This immediate project will have a direct impact on supply reliability in central Toronto and is a common element of the potential long term supply path options. This project involves the construction and operation of two new underground, 115 kilovolt (kV) electrical transmission lines between the John Transformer Station (TS) and the Esplanade TS.

All of the options identified to date are subject to Environmental Assessment (PDF 2.2 MB) and Ontario Energy Board review and approval. These processes provide additional opportunities for input from the local community and other stakeholders.

Timeline

Click on a timeline box below for more details.



Still have questions?

View our Frequently Asked Questions

If you would like more information about this project and/or want to be on our project mailing list, please contact:

Community Relations
Hydro One Networks Inc.
Tel: 1-877-345-6799 or 416-345-6799
Fax: 416-345-6984
E-mail: community.relations@HydroOne.com

 

Supply to Downtown Toronto - Transmission Line Project


May 2004

Initiate consultation process

Utilities
Hydro One has been working with the local utility, Toronto Hydro, to ensure that together, we can accommodate load growth and continue to reliably supply electricity to the many residents and businesses in downtown Toronto.

Local Elected Official and Staff
Hydro One has provided project briefings to various City of Toronto staff members.

Public Information Centre
Hydro One held a Public Information Centre on April 29, 2004. Through a series of session panels (PDF 7.8 MB), brochures (PDF 69 KB) and discussions, interested parties were informed of the need for the project, the options being considered and the process. From these sessions the public was able to give us valuable feedback.



May-June 2004

Meet with interested stakeholders to address concerns

Interested Stakeholders
Meetings with various stakeholder groups continue to provide valuable input in the assessment of route alternatives.

As part of stakeholder consultations, Hydro One has attended several meetings of the Toronto Public Utilities Coordinating Committee to brief the members on this plan and to coordinate the project with the planned works of the various City departments and other utilities represented on the Committee. Hydro One has also met with the St. Lawrence Business Improvement Association to discuss and address their concerns.

 



June - August 2004

Select preferred route and present at Public Information Centres

A Public Information Centre was held on June 29, 2004 and a preliminary preferred route was presented. As proposed, the preliminary preferred route was to be a deep tunnel under Front and Sherbourne Streets. Through a series of session panels (PDF 13.4 MB), brochures (PDF 318 KB) and discussions, interested parties were informed of the route and deep tunnel construction method.

A Public Information Centre was held on August 5, 2004 to present a modified route. As a result of additional technical review, Hydro One proposed that the route portion located on Sherbourne Street be moved to Frederick Street. Construction of the route portions on Front and Frederick Streets would use the deep tunnelling method. Through a series of session panels (PDF 7.2 MB), brochures (PDF 466 KB) and discussions, interested parties were informed of the route modification.



September 2004

Draft Environmental
Study Report available
for review

Draft Environmental Study Report
Hydro One has completed the Class Environmental Assessment (EA) for the Supply to Downtown Project. In accordance with environmental review requirements, the Class EA Environmental Study Report (PDF 15.7 MB, High-speed Internet connection recommended) is available for stakeholder review and comment for a 30-day period from September 10, 2004 to October 12, 2004.

Stakeholder questions or comments on the Environmental Study Report must be received no later than 4:30 p.m. on Tuesday, October 12, 2004 by John Monczka, Hydro One, at 483 Bay Street, North Tower TCT 14, Toronto, Ontario, M5G 2P5, fax 416-345-6919, or e-mail j.monczka@HydroOne.com.



Spring 2005

Plan approved

Hydro One received Class EA and Ontario Energy Board approvals for the project. Both were necessary before construction could begin.



Spring 2005
Construction began

Construction began with excavation of a large entry shaft at Esplanade Transformer Station at the southwest corner of Sherbourne and The Esplanade. Soon after, a tunnel boring machine was delivered to the site and began to bore the tunnel deep below the city.



October 2006
Tunnel boring machine emerges at John Transformer Station

The first stage of the tunnel construction process ended on October 23, 2006 when the tunnel boring machine was lifted out of a shaft excavated on the side of John Street between Hydro One's John Transformer Station and the CBC Headquarters building.

Tunnel boring machine
The Tunnel boring machine emerges on John Street between the CBC Headquarters and the John Transformer Station.  This machine is now a veteran of three tunnels.  It is owned by underground excavation contractor, Dibco.  After removal, the machine travelled to Dibco’s workshops for an overhaul, and will then begin work on another tunnel.



October 2006 to
December 2007
Tunnel concreting and cable installation

Work to line the tunnel with concrete is now complete.  And crews are in the final stages of connecting the six large cables in the tunnel.



Tunnel boring machine
A section of the concreted tunnel that runs under Jarvis Street.

Reel face on
Cable arrived from France in 19 steel reels sealed with steel on the
sides to protect their valuable contents.

Cable reel at Esplanade
The cable was carefully rolled into the tunnel: first from the
Esplanade TS end, shown here; later from the John end.

Clamping cable on the Esplanade
Cables are then firmly clamped to the walls of the vertical shafts and
tunnel.  This is the vertical shaft at the Esplanade TS end of the tunnel.

Buried cables
Once the cables emerge from the Esplanade shaft, they proceed through a trench
lined with compacted limestone screenings that leads to the Esplanade TS Switchyard.

Electronic markers in trench
After the cables are laid, they are covered by another layer of compacted limestone screenings. The red square in the foreground is a electronic marker that will allow for easy cable locates once the cables are buried.

Red concrete to protect underground lines
A layer of red concrete was then poured over the compacted sand to act as a
physical barrier to protect the cable from errant backhoes in the future.



Spring 2008
Lines go into service

Following installation of circuit breakers at both Esplanade Transformer Station and John Transformer Station, the lines will go into service at 115,000 volts. The lines are designed to eventually double their capacity by switching to 230,000 volts when extra capacity is needed in the future. The tunnel is also designed to accommodate six additional 230,000 volt cables should they be needed because of further growth in the city centre.


 

 


 

[ Printable Version ]

All contents © 2008 Hydro One Networks Inc. All rights reserved.
Privacy and Terms of Use

June - Aug 2004 May - June 2004 May 2004 September 2004