|
 |
Home > In Your Community > New Projects > Transmission System Projects
Last Updated January 23, 2008
Transmission System Projects - Supply to Downtown Toronto
What's New
- The tunnel linking Hydro One's Esplanade Transformer Station and John
Transformer Station in downtown Toronto is now complete.
- Final commissioning work is well underway to allow the new double
circuit 115 kV underground transmission line in the tunnel to go into
service in January 2008.
- Hydro One is consulting with residents who live in the vicinity of
Esplanade Transformer Station on site improvement options, including
a new perimeter fence/wall and landscaping to be installed in 2008.
- See photos of construction progress below.
Background
Toronto is Canada's largest city and plays a significant role in both
the provincial and national economy. Hydro One transmits power to Toronto
Hydro, the local distribution company that distributes electricity to
customers in the city. A safe and reliable supply of electricity to the
city is critical to the continued growth and prosperity of both Toronto
and Ontario. This is especially true for the downtown core, home to the
Toronto Stock Exchange, many corporate head offices and a significant
number of diverse industries and commercial activity.
The
need for electricity in Toronto is forecast to continue to grow at a steady
pace. This growing demand for electrical supply means upgrading the transmission
system serving downtown to maintain reliable electricity supply to the
city. Hydro One and Toronto Hydro, the local distribution company, agree
that new facilities are required. Within Hydro One's 10 year planning
period a new supply path to central Toronto will be required. However,
a more immediate need is to reinforce the existing transmission infrastructure.
This will improve the reliability of supply to downtown Toronto.
This immediate project will have a direct impact on supply reliability
in central Toronto and is a common element of the potential long term
supply path options. This project involves the construction and operation
of two new underground, 115 kilovolt (kV) electrical transmission lines
between the John Transformer Station (TS) and the Esplanade TS.
All of the options identified to date are subject to Environmental
Assessment (PDF 2.2 MB) and Ontario Energy Board review and approval.
These processes provide additional opportunities for input from the local
community and other stakeholders.
Timeline
Click on a timeline box below for more details.

Still have questions?
View our Frequently
Asked Questions
If you would like more information about this project and/or want to
be on our project mailing list, please contact:
Community Relations
Hydro One Networks Inc.
Tel: 1-877-345-6799 or 416-345-6799
Fax: 416-345-6984
E-mail: community.relations@HydroOne.com
| Supply to Downtown Toronto
- Transmission Line Project |
|

May 2004
Initiate consultation process
|
Utilities
Hydro One has been working with the local utility, Toronto Hydro,
to ensure that together, we can accommodate load growth and continue
to reliably supply electricity to the many residents and businesses
in downtown Toronto.
Local Elected Official and Staff
Hydro One has provided project briefings to various City of Toronto
staff members.
Public Information Centre
Hydro One held a Public Information Centre on April 29, 2004. Through
a series of session panels
(PDF 7.8 MB), brochures
(PDF 69 KB) and discussions,
interested parties were informed of the need for the project, the
options being considered and the process. From these sessions the
public was able to give us valuable feedback.
|
|
|
|

May-June 2004
Meet with interested stakeholders to address concerns
|
Interested Stakeholders
Meetings with various stakeholder groups continue to provide valuable
input in the assessment of route alternatives.
As part of stakeholder consultations, Hydro One has attended several
meetings of the Toronto Public Utilities Coordinating Committee
to brief the members on this plan and to coordinate the project
with the planned works of the various City departments and other
utilities represented on the Committee. Hydro One has also met with
the St. Lawrence Business Improvement Association to discuss and
address their concerns.
|
|
|
|

June - August 2004
Select preferred route and present at Public Information Centres
|
A Public Information Centre was held on June 29, 2004 and a preliminary
preferred route was presented. As proposed, the preliminary preferred
route was to be a deep tunnel under Front and Sherbourne Streets.
Through a series of session panels
(PDF 13.4 MB), brochures
(PDF 318 KB) and discussions, interested parties were informed of
the route and deep tunnel construction method.
A Public Information Centre was held on August 5, 2004 to present
a modified route. As a result of additional technical review, Hydro
One proposed that the route portion located on Sherbourne Street
be moved to Frederick Street. Construction of the route portions
on Front and Frederick Streets would use the deep tunnelling method.
Through a series of session panels
(PDF 7.2 MB), brochures
(PDF 466 KB) and discussions, interested parties were informed of
the route modification.
|
|
|
|

September 2004
Draft Environmental
Study Report available
for review
|
Draft Environmental Study Report
Hydro One has completed the Class Environmental Assessment (EA)
for the Supply to Downtown Project. In accordance with environmental
review requirements, the Class EA Environmental
Study Report (PDF 15.7 MB, High-speed Internet connection recommended)
is available for stakeholder review and comment for a 30-day period
from September 10, 2004 to October 12, 2004.
Stakeholder questions or comments on the Environmental Study Report
must be received no later than 4:30 p.m. on Tuesday, October
12, 2004 by John Monczka, Hydro One, at 483 Bay Street, North
Tower TCT 14, Toronto, Ontario, M5G 2P5, fax 416-345-6919, or e-mail
j.monczka@HydroOne.com.
|
|

Spring 2005
Plan approved
|
Hydro One received Class EA and Ontario Energy Board approvals
for the project. Both were necessary before construction could begin.
|
|

Spring 2005
Construction began
|
Construction began with excavation of a large entry shaft at Esplanade
Transformer Station at the southwest corner of Sherbourne and The
Esplanade. Soon after, a tunnel boring machine was delivered to
the site and began to bore the tunnel deep below the city.
|
|

October 2006
Tunnel boring machine emerges at John Transformer Station
|
The first stage of the tunnel construction process ended on October
23, 2006 when the tunnel boring machine was lifted out of a shaft
excavated on the side of John Street between Hydro One's John Transformer
Station and the CBC Headquarters building.

The Tunnel boring machine emerges on John Street between the CBC
Headquarters and the John Transformer Station. This machine
is now a veteran of three tunnels. It is owned by underground
excavation contractor, Dibco. After removal, the machine travelled
to Dibco’s workshops for an overhaul, and will then begin
work on another tunnel.
|
|

October 2006 to
December 2007
Tunnel concreting and cable installation
|
Work to line the tunnel with concrete is now complete. And crews are in the final stages of connecting the six large cables in the tunnel.

A section of the concreted tunnel that runs under Jarvis Street.

Cable arrived from France in 19 steel reels sealed with steel on
the
sides to protect their valuable contents.

The cable was carefully rolled into the tunnel: first from the
Esplanade TS end, shown here; later from the John end.

Cables are then firmly clamped to the walls of the vertical shafts
and
tunnel. This is the vertical shaft at the Esplanade TS end
of the tunnel.

Once the cables emerge from the Esplanade shaft, they proceed through
a trench
lined with compacted limestone screenings that leads to the Esplanade
TS Switchyard.

After the cables are laid, they are covered by another layer of
compacted limestone screenings. The red square in the foreground
is a electronic marker that will allow for easy cable locates once
the cables are buried.

A layer of red concrete was then poured over the compacted sand
to act as a
physical barrier to protect the cable from errant backhoes in the
future.
|
|

Spring 2008
Lines go into service
|
Following installation of circuit breakers at both Esplanade Transformer
Station and John Transformer Station, the lines will go into service
at 115,000 volts. The lines are designed to eventually double their
capacity by switching to 230,000 volts when extra capacity is needed
in the future. The tunnel is also designed to accommodate six additional
230,000 volt cables should they be needed because of further growth
in the city centre.
|
|
|
|
|
 |